Procedure for obtaining Domestic/Commercial Service Connection

  • Apply for your Domestic or commercial service connection in Online
  • Enter all the particulars required in the application form. Produce proper  documents/records to prove the legal ownership of the premises for which electricity supply is required (Form-1).
  • An intending consumer who is not the owner of the premises he occupies shall produce a consent letter in Form-5 of Annexure III to the Tamil Nadu Electricity Distribution Code from the owner of the premises for availing the supply. If the owner is not available or he refuses to give consent letter, the intending consumer shall produce valid proof of his/her being in occupation of the premises and also execute an indemnity bond in Form 6 of Annexure III and acceptance to pay security deposit twice the normal rate.
  • Submit the application Online and obtain proper acknowledgement.

The following documents shall be accompanied with the application:
  1. Certified copy of proof of ownership such as sale deed/partition deed/gift settlement/allotment letter/Computer Patta/ownership certificate issued by revenue department officials/ court judgement or recent property tax receipt
  2. In case of joint property, certified copies of proof of ownership such as legal heir certificate along with parent documents specified in note (i) above and consent letters from co-owners. If consent letter is not produced, an indemnity bond with enhanced security deposit
  3. If the applicant is not the owner, consent letter from owner in Form No. 5 or valid proof of occupancy and indemnity bond in Form No.6.
  4. As per Division Bench Order dated 23.8.2006, for all special/multistoried buildings in Chennai Metropolitan area, Planning permit from competent authority has to be submitted along with application and Completion Certificate from competent authority has to be submitted before effecting supply.
  • Upon receipt of an application for supply of electricity, a notice will be sent to the intending consumer that he or his/her authorized representative to meet the Engineer to agree on the position of the point of supply/ space for fixing the meter at a convenient place in the ground floor with  easy accessibility for inspection.
  • In all storied buildings, irrespective of the number of floors, provide space for fixing meter, cut -out etc., in the ground floor.
  • Advice Slip/notice/Letter will be issued indicating the prescribed charges payable within stipulated period from the date of receipt of advice.
  • On receipt of charges only, extension works will be taken up and executed.
  • Intending consumer shall permit the licensee, free of cost the use of any land belonging to the consumer which may be required for erecting poles, lines, etc.
  • Get all the wiring work done by authorised person specified by the authority. After completion of the wiring, notice must be sent to the Engineer by the intending consumer (upon printed test report form obtainable free of cost from the offices of the TANGEDCO) that the installation has been completed and tested and that the same is complete and ready for inspection and test by the Engineer.
  • A notice will be sent to the intending consumer to avail supply within stipulated period.
  • Apply for your Domestic or commercial service connection in the prescribed form  (Form-1) obtainable free of cost from the Section Office.  
  • Enter all the particulars required in the application form. Produce proper documents/records to prove the legal ownership of the premises for which electricity supply is required (Form-1).

The intending consumer shall comply any decree or order or judgment of any civil court in regard to the supply of electricity or other requirements mentioned in such decree or order or judgment.

Save-energy1 Energy / Electricity Saved is Energy ProducedSave-energy2 Energy conservation, a key to sustainable developmentSave-energy3 Energy is in limited supply, Use it wiselySave-energy4 Turn off lights and equipments when not in useSave-energy5 Save energy for benefit of self and nation   Save-energy1 Install RCD to safeguard life from Electrical Accidents   Save-energy1 To make earth greener, switch over to electric vehicles   Save-energy1 Support innovative electric vehicle technology to protect our mother earth   Save-energy1 Electric vehicle does not make noise   Save-energy1 Go green with electric vehicles   Save-energy1 Shape the future with electric vehiclesSave-energy1 Save future generations by using electric vehiclesSave-energy1 Save Fuel, Save Money, Switch to electric vehicleSave-energy1 Make a Change with Electric vehicleSave-energy1 Electric vehicle: A Brighter FutureSave-energy1 Electric vehicle: No Fumes, No Noise, No Pollution