World Bank aided Coastal Disaster Risk Reduction Project(CDRRP)

Conversion of HT & LT overhead lines into HT & LT cables in cyclone prone coastal towns (CDRRP)

TANGEDCO has implemented conversion of HT and LT overhead lines into HT and LT underground cables in cyclone prone coastal towns of Cuddalore, Nagapattinam and Velankanni with revised administrative sanction of Rs.406.83 crore with the funding assistance from World Bank through GoTN.

Three packages ( Two packages (Package-3 & 2) in Cuddalore Town and one package (Package-7) in Velankanni Town (Nagapattinam Dt)) were awarded under total turnkey Contract for Rs.406.83 Cr. to M/s.L&T Ltd.( Cuddalore packages) and M/s Polycab India Ltd. ( Velankanni package).

The 100% contract works were completed for Package -3 on 15.10.2022; Package-7 on 15.09.2022; Package-2 on 31.12.2022

The Operation & Maintenance Manual and As-built drawings for Package-3 Cuddalore are furnished below:

ENVIRONMENT & SOCIAL ASSESSMENT (ESA)

Sl.No.

Areas Covered

Details

1Karaiyeravittakuppam, Sandrorpalayam, Brookspet, Cuddalore O.T., Saibaba Nagar, S.N. Chavadi, Arundodhi Nagar, SIPCOT, Sangolikuppam, Echankadu, KudiKadu.  Package3 cuddalore
2Velankanni-Church, Serudur, ECR, Uppalam, Thideerkuppam, Tsunami colony, Pookara street, Karamathumedu, Sivan Kovil and Keechakuppam in Velankanni Town Panchayat.  package7 Nagapattinam
3Karaiyeravittakuppam, Sandrorpalayam, Brookspet, Cuddalore O.T., Saibaba Nagar, S.N. Chavadi, Arundodhi Nagar, SIPCOT, Sangolikuppam, Echankadu, KudiKadu.  Package3 summary in TAMIL
4CDRRP-Coastal Regulation Zone(CRZ) clearance accorded by MoE, FCC on 3.10.2017 for Cuddalore Town, Cuddalore Dt  Clearance Letter-CRZ
5UG Electrical Cable Works Covering Cuddalore Municipality (Vinayaga Nagar, Semmandalam, Varadharajan Nagar, Annandale, Sorakalpattu, Seetharam Nagar, Pudupalayam, R.P. Nagar, Kamaraj Nagar, Devanampattinam, Sothikkuppam, Sivanandhapuram, Sellankuppam, VSR Palayam etc. settlements of Cuddalore Municipality)  Package2 Cuddalore EA Report
6UG Electrical Cable Works Covering Cuddalore Municipality (Vinayaga Nagar, Semmandalam, Varadharajan Nagar, Annandale, Sorakalpattu, Seetharam Nagar, Pudupalayam, R.P. Nagar, Kamaraj Nagar, Devanampattinam, Sothikkuppam, Sivanandhapuram, Sellankuppam, VSR Palayam etc. settlements of Cuddalore Municipality)  Package2 Cuddalore SA and MP Report
7CDRRP-Coastal Regulation Zone(CRZ) clearance accorded by MoE, FCC on 25.10.2018 for Nagapattinam Town, Nagapattinam Dt  Clearance Letter-CRZ

Save-energy1 Energy / Electricity Saved is Energy ProducedSave-energy2 Energy conservation, a key to sustainable developmentSave-energy3 Energy is in limited supply, Use it wiselySave-energy4 Turn off lights and equipments when not in useSave-energy5 Save energy for benefit of self and nation   Save-energy1 Install RCD to safeguard life from Electrical Accidents   Save-energy1 To make earth greener, switch over to electric vehicles   Save-energy1 Support innovative electric vehicle technology to protect our mother earth   Save-energy1 Electric vehicle does not make noise   Save-energy1 Go green with electric vehicles   Save-energy1 Shape the future with electric vehiclesSave-energy1 Save future generations by using electric vehiclesSave-energy1 Save Fuel, Save Money, Switch to electric vehicleSave-energy1 Make a Change with Electric vehicleSave-energy1 Electric vehicle: A Brighter FutureSave-energy1 Electric vehicle: No Fumes, No Noise, No Pollution